Brooks Hill and Jefferson Avenue 2025

Brooks Hill School and Jefferson Avenue School

Fairport for the Future 2025 at Brooks Hill and Jefferson Avenue

The unique character and needs of the Brooks Hill and Jefferson Avenue school facilities have defined the scope of the project at these two schools. The Fairport for the Future 2025 project proposals for Brooks Hill and Jefferson Avenue include cafeteria renovations, classroom and toilet room modernization, as well as upgrades to air conditioning and flooring, while maintaining the 0% additional tax increase to our community.

A floor plan shows the Brooks Hill Elementary School renovation project, including highlighted areas for new flooring, air conditioning, classroom renovations, bathroom renovations and health and safety updates.Scope of proposed work at Brooks Hill School:

  • Partial classroom renovations in select classrooms, including walls and classroom bathrooms
  • SPARK Lab finshes
  • Cafeteria finishes and air condition
  • Corridor ceilings, flooring and lighting

 

Health and safety and Building Condition Survey projects:

  • Fire alarm system upgrades
  • Upgrades and replacement of original HVAC equipment
  • Electrical panel replacement
  • Building controls upgrades
  • Public address (PA) and clock system upgrades
  • Ventilation and air management updates

 

A floor plan shows the Jefferson Avenue Elementary School renovation project, including highlighted areas for new flooring, air conditioning, classroom renovations, bathroom renovations and health and safety updates.Scope of proposed work at Jefferson Avenue School:

  • Full cafetorium renovation, including flooring, finishes, ceilings, lighting and air conditioning
  • Kitchen renovation, including new finishes and appliances
  • Select toilet room walls, finishes and fixtures

Health and safety and Building Condition Survey projects:

  • Fire alarm system upgrades
  • Upgrades and replacement of original HVAC equipment
  • Electrical panel replacement
  • Building controls upgrades
  • Public address (PA) and clock system upgrades
  • Ventilation and air management updates
  • A floor plan shows the Brooks Hill Elementary School renovation project, including highlighted areas for new flooring, air conditioning, classroom renovations, bathroom renovations and health and safety updates.Scope of proposed work at Brooks Hill School:

    • Partial classroom renovations in select classrooms, including walls and classroom bathrooms
    • SPARK Lab finshes
    • Cafeteria finishes and air condition
    • Corridor ceilings, flooring and lighting

     

    Health and safety and Building Condition Survey projects:

    • Fire alarm system upgrades
    • Upgrades and replacement of original HVAC equipment
    • Electrical panel replacement
    • Building controls upgrades
    • Public address (PA) and clock system upgrades
    • Ventilation and air management updates

     

  • A floor plan shows the Jefferson Avenue Elementary School renovation project, including highlighted areas for new flooring, air conditioning, classroom renovations, bathroom renovations and health and safety updates.Scope of proposed work at Jefferson Avenue School:

    • Full cafetorium renovation, including flooring, finishes, ceilings, lighting and air conditioning
    • Kitchen renovation, including new finishes and appliances
    • Select toilet room walls, finishes and fixtures

    Health and safety and Building Condition Survey projects:

    • Fire alarm system upgrades
    • Upgrades and replacement of original HVAC equipment
    • Electrical panel replacement
    • Building controls upgrades
    • Public address (PA) and clock system upgrades
    • Ventilation and air management updates
Concept

Partial classroom renovations at Brooks Hill Elementary School

The proposed Fairport for the Future 2025 Capital Improvement Project features partial renovations in the majority of the classrooms in Brooks Hill. These renovations include new lighting and finishes, along with an overhaul of the attached classroom bathrooms. These bathrooms will feature new plumbing, fixtures and finishes.

Concept

Cooling large group spaces at Brooks Hill

The cafeteria at Brooks Hill serves as much more than a place to enjoy an amazing FCSD school meal - the multi-purpose space serves as a rehearsal and performance space, a meeting area and an assembly room. The Fairport for the Future 2025 Capital Improvement Project proposes to update this space with modern lighting, flooring, wall finishes and air conditioning, while keeping the beloved character of Brooks Hill's gathering space.